Measure the wind where turbines turn: 50 metres and above.
Côte d'Ivoire has almost no reliable wind data at the heights that matter. The idea: fit certified wind sensors to telecom towers that already stand across the country: about 25 sites, 24 months, and data that belongs to the country.
A 10-metre station cannot tell you what a turbine will see
The wind gets stronger and steadier as you go up, away from trees, buildings and rough ground. Most weather stations in the country sit around 10 m, so they understate the wind a turbine would actually catch. That gap is not small: the energy in the wind rises with the cube of its speed, so 20% more wind means about 70% more energy.
Village and community turbines work at 15 to 40 m, medium turbines at 50 m and above, and large wind farms at 100 to 120 m. Without measured data at those heights, no ministry, bank or investor can size a project with confidence, and good sites stay invisible.
Use the towers that already stand
Instead of building a handful of expensive masts, we put class-1 wind sensors on existing telecom towers, starting with the country's largest network. For the cost of a few masts, the country gets about 25 measurement sites.
Two or three heights per tower
Sensors at, for example, 30, 45 and 60 m, and up to 80–100 m where the tower allows, on side booms that follow the international standard (IEC 61400-12-1) to limit the tower's shadow.
Installed by the crews who already climb
The tower maintenance teams fit and check the sensors, for a fee. No new construction, no civil works, no building permits.
Self-powered, sending data every day
Each station has its own small solar panel and battery, and sends its data over the mobile network to a central database. A satellite option covers the few areas without signal.
Checked up to turbine height
A lidar, a laser instrument that reads the wind up to 200 m, moves from site to site every few months to confirm how the wind changes above the towers, up to 100–120 m.
The most promising zones first
Priority goes to the north and north-east: Bondoukou, the Bounkani (Bouna) and the Tchologo (Ferkessédougou, Ouangolo, Kong), then Odienné in the north-west and Tabou on the western coast, with San-Pédro and Divo as options. Several towers per zone let us compare neighbouring sites.
- Data that belongs to the country. Open formats, readable on the logger itself, no mandatory subscription, and a contract stating that the measurements are owned by the State. The final wind atlas is published openly.
- A new generation of Ivorian technicians. The data arrives in a monitoring room at Université Félix Houphouët-Boigny (LABTECH, our partner since 2016), linked to regional universities that each adopt the stations near them. Students learn to check, correct and analyse the data and join the maintenance visits.
- Experience behind it. Through the Wind Empowerment network we can call on experts in both small and large wind, including large-turbine installation.
How it would run
Two months to select the towers and agree access, three months to buy the equipment and set up the monitoring room, then 24 months of measurements with quarterly reports and a final wind atlas published openly. The number of sites can be adjusted to the budget available.
Read the full concept note
The full concept note, with the technical details and the indicative budget, is available on request.